Downtown Construction Update for the week of March 25, 2019

Road-Work-Sign

During the week of March 25, 2019, downtown construction contractors will continue installing drainage on School Street and Church Street. Parking on School Street will be prohibited during construction hours. Both Church and School may be closed to through traffic at times. Local traffic will be allowed and motorists and pedestrians are asked to use caution when traveling in these areas.

Looking ahead, drainage on Elm Street will begin later in the week or beginning the week of April 1. Parking and traffic may be impacted during these times, but streets will remain open to traffic. All schedules are weather permitting and subject to change. Sidewalk work on Railroad Street is scheduled to begin mid or late April.

Work will take place 7 a.m. to 3:30 p.m. Monday-Friday. All inquiries can be directed to the Town’s Department of Public Works at (413) 528-0867, or to Public Works Superintendent Sean Van Deusen, svandeusen@townofgb.org.